Contract Award Notice – San Jose Village and San Pablo Village Joint Water Supply System Rehabilitation

 

CONTRACT AWARD INFORMATION – WORKS

BELIZE SOCIAL INVESTMENT FUND

SAN JOSE VILLAGE AND SAN PABLO VILLAGE JOINT WATER SUPPLY SYSTEM REHABILIATION, ORANGE WALK DISTRICT, BELIZE

  

  1. Bid Prices:

 

Names of Bidders Submitting Bids Country of Bidder Bids Prices at Bid Opening 

(Belize Currency)

Corrected Bid

Prices 

(Belize Currency)

 

Isaac Ranguy 

 

 

Belize

 

 

$ 1,188,590.00

 

 

$1,188,340.00

 

FT Williams &

Associates Ltd.

 

 

Belize

 

 

$ 1,489,440.05

 

 

 

$ 1,489,440.05

 

 

  1. Number Bids Rejected for Non-Responsiveness: 1 Bidder (FT Williams & Associates Ltd.)
  2. Winning Bidder: Isaac Ranguy
  3. Winning Bid Price: BZD $1,188,340.00
  4. Commencement Date of Contract: April 26, 2021
  5. Duration of Contract: Over a period of eight (8) months

   

Summary Scope of Contract:  

 

The contract includes for the supply and installation of all requisite materials, equipment, and relevant appurtenances for approximately 15,000 feet of polyvinyl chloride (PVC) transmission and distribution lines; installation of approximately 900 service connections; construction of pumping facilities; and the installation of all requisite electrical works. Works will also include for the construction of a chain link perimeter fence which will cordon the pumping facilities and storage facilities.